Over 90 percent work completed on Chandni Chowk Redevelopment ProjectIllustrative image – not actual.
Over 90 percent of the work on the central verge of 1.3-km-long section at Chandni Chowk in Old Delhi has already been completed. While the area is open to pedestrians, the inauguration for the same is likely to take place in April-May 2021. 
 
Horticulture work on the central verge as well as paintings on the grills will be completed by 20 February 2021. Around 15-20 light poles with CCTVs have been set up and more light poles are being added. 
 
Some work near Red Fort junction, Town Hall and Sunehri Masjid junction is yet to be completed. 
 
The area that housed the Hanuman Mandir earlier, which was bulldozed in January 2021, has been repaired now and covered with tiles. Near the entry to the stretch, a washroom has been built, while work on three other washrooms is underway. The rest of the three washrooms are situated near Fountain Chowk, Bhagirath Place and Town Hall. 
 
The washroom near Bhagirath Place is expected to be completed by the end of February 2021. 
 
Work on Phase-II, which involves restoring six arterial roads as well as building facades, is underway. The estimates for the same are being prepared by government departments.