Over 55 percent work of Chennai-Bengaluru Expressway completed in TNIllustrative image – not actual.

Over 55 percent of the work to construct the four-lane brownfield Bengaluru-Chennai Expressway (BCE) has been completed in Tamil Nadu, and entails a cost of Rs 5,971 crore. The access-controlled road will pass through Andhra Pradesh and Karnataka.

National Highways Authority of India (NHAI) is executing the project, and anticipates completion by the end of the calendar year. In Tamil Nadu, the work is being carried out in four packages, and the road will have three rest areas, two truck lay-bys, 34 major bridges, 31 minor bridges, three rail overbridges, and three interchanges. The stretch between Walajapet and Arakkonam is the fastest progressing one, with 62.22 percent of it being completed, as per NHAI.

Karnataka has completed 87 percent of the work at a cost of Rs 5,465.08 crore, and the stretch will have four grade separators, 15 major bridges, 47 minor bridges, 63 underpasses, four toll plazas, and one truck lay-by. In Andhra Pradesh, the work is being carried out on three stretches for a total cost of Rs 4,259 crore, and road-laying work has started in all the stretches. At an average, 40 percent of the work has been completed so far.

The complete length of the under-construction BCE Project is around 258 km. It will pass through seven districts - Bangalore Urban, Bangalore Rural, and Kolar in Karnataka, Chittoor in Andhra Pradesh, and Vellore, Kancheepuram, and Tiruvallur in Tamil Nadu.

← All latest storiesBack to top →