Over 55 percent work completed on Lekki Deep Sea Port in NigeriaIllustrative image – not actual.
Lekki Deep Sea Port, the largest seaport of Nigeria that is being developed at Lagos Free Trade Zone (LFTZ) in Ibeju Lekki, is currently 55.48 percent complete. 
 
Lekki Port LFTZ Enterprise is the developer of the project.
 
The dredging and reclamation works have reached 61.11 percent completion, the Quay Wall 50.39 percent, breakwater 67.49 percent, and the landside infrastructure development 33.70 percent.
 
The project is on course and going according to schedule. 
 
At the end of Q3/2022, the entire construction works will be complete and the facility will commence commercial operations by Q4/2022 as planned.