As many as 478 infrastructure projects, each worth Rs 150 crore or more, have seen cost overruns totalling more than Rs 4.4 lakh crore.
The Ministry of Statistics and Programme Implementation monitors infrastructure projects worth Rs 150 crore and above. Of the 1,768 projects, 478 reported cost overruns and 525 were delayed.
The total original cost of implementation of 1,768 projects was Rs 22,86,955.18 crore and their anticipated completion cost is likely to be Rs 27,27,220.47 crore, which reflects overall cost overruns of Rs 4,40,265.29 crore, a 19.25 percent of original cost.
The expenditure incurred on these projects till May 2021 is Rs 13,30,533.53 crore, which is 48.79 percent of the anticipated cost of the projects.
The number of delayed projects decreases to 387 if delay is calculated on the basis of the latest schedule of completion. Moreover, for 995 projects neither the year of commissioning nor the tentative gestation period has been reported.
Of the 525 delayed projects, 100 projects have an overall delay in the range of one to 12 months, 124 projects (13-24 months), 182 projects (25-60 months) and 119 projects (61 months and above). The average time overrun in these 525 delayed projects is 46.36 months.
The reasons for time overruns as reported by various project implementing agencies include delay in land acquisition, delay in obtaining forest and environment clearances, and lack of infrastructure support and linkages, delay in tie-up for project financing, delay in finalisation of detailed engineering, change in scope, delay in tendering, ordering and equipment supply, etc.
Also, the state-wise lockdown due to COVID-19has also caused delay in implementation of these projects.