Illustrative image – not actual.A pre-feasibility report has estimated the cost of the outer harbour project at Tuticorin at Rs.4,350 crore.
National Maritime Development Programme (NMDP) of the shipping ministry had earlier estimated the outer harbour project to be around Rs.2,150 crore. This, however, did not include construction of superstructures like breakwater that would cost over Rs.1,500 crore.
As part of the project, two breakwaters - one in the North-South direction of 3.1 km and another in South-East of 4.2 km - will be constructed. Initially, the outer harbour will have 1.5 km long container terminal to be developed by a BOT (build, own and transfer) basis. Subsequently, different developers will construct facilities to handle coal, POL (petroleum, oil and lubricants) and general cargo. The TPT is considering giving the entire project to private sector, and alternatives for financing the development of infrastructure and superstructures by the port to the BOT operator.
The port trust had sent the memorandum of the project to the Private Public Partnership Appraisal Committee for approving the construction works. The report was also sent to the Department of Economic Affairs for viability gap funding - to reduce capital cost of the project by credit enhancement and to make the project viable and attractive for private investments.
Creation of additional facilities and upgrading the existing facilities at inner harbour are under implementation and expected to be completed by 2008.
The proposed harbour will have a capacity to handle 22 million tpa of cargo in 2011-12. The project will augment the capacity of the existing harbour, whose capacity is also being expanded from 16 million tpa now to 36 million tpa by 2009. Thus, in another five years, the southern port will be able to handle close to 60 million tpa.