Oudh Sugar plans Rs.479 crore expansionIllustrative image – not actual.

Oudh Sugar Mills is in the process of implementing various projects with an estimated investment of Rs.479 crore. With the completion of these projects, the company will have a aggregate crushing capacity of 28,700 tccpd, captive power generation of 30 MW and two distilleries of 75 klpd.

The progress of the company is as follows:

Hargaon Sugar Mills, a unit of Oudh Sugar Mills at Hargaon in Uttar Pradesh, is expanding cane crushing capacity from 7,500 tccpd to 10,000 tccpd with a co-generation plant of 8 MW. The project entailing an investment of Rs.116.06. crore is scheduled for completion by October 2006.

The sugarcane crushing capacity of New Swadeshi Sugar Mills, Narkatiaganj (Bihar), a unit of the company, is  being expanded from 6,500 tccpd to 7,500 tccpd, along with a co-generation plant of 5 MW at a cost Rs.27 crore.

The company is also in the process of setting up a 7,000 tccpd sugar unit along with a 17 MW power unit at Hatta in Gorakhpur district of Uttar Pradesh at an estimated cost of Rs.336 crore The project is scheduled for completion by November 2008.

Currently, the company has three sugar manufacturing units (two in U.P. and one in Bihar) and will achieve an aggregate crushing capacity of about 21,700 tccpd by 2007. It has also two distilleries at Hargaon (U.P.), Narkatiaganj (Bihar) and a fruit & vegetable processing factory at Allahabad (U.P).