Illustrative image – not actual.ONGC Tripura Power Company's (OTPC) 727 MW gas based project is on fast track as the Bangladesh Government has agreed to provide transit facility through Ashuganj port for transportation of heavy duty equipment.
According to sources, General Electric (GE) has already shipped the first turbine of 363.3 MW from the US which will reach Haldia port in West Bengal in July 2010 and is scheduled to start its journey for Ashugunj river port, located close to the OTPC project site at Palatana in Tripura, after the September 2010. The Unit I is slated to start commercial generation in December 2011.
A consortium of BHEL and GE is the EPC contractor for the power project. The second unit is scheduled to start generation in March 2012.