The 363 MW Unit-II, which recently started synchronised production, has been trying to reach optimum output level through fine tuning of all the operational metrics. It will start the full test run soon.
Work on the 650 km transmission line, which will connect the OTPC project with the North-Eastern grid at Bongaigaon in Assam is also on its last lap. Only 13 km of line is required to be erected for grid connection.
With the completion of this transmission line, the Rs 10,000 crore project could be connected to the grid in the first week of January.
Unit-II of the 726.6 MW (2 x 363.3 MW) Palatana power project in Udaipur, Tripura, was inaugurated by Prime Minister, Narendra Modi, on 1 December, 2014.
The investment for the project is about Rs 4,000 crore in power plants; Rs 2,000 crore in electricity transmission; and Rs 4,000 crore in the development and production of gas.
More Project Info:
Tripura Power Project