Illustrative image – not actual.Villages in the outer ring road (ORR) limits will receive drinking water connections as soon as the project starts in August 2017. The work is expected to be completed by June 2018.
The Hyderabad Metropolitan Water Supply and Sewerage Board (HMWS&SB) will lay pipelines and construct 403 reservoirs in seven municipalities. This will facilitate water supply to 183 villages.
Phase 1 will take up construction of 67 reservoirs. Work on these reservoirs is expected to be completed by February 2018.
The new project will add to the already existing reservoir with a capacity of one million ltr.
The project is estimated to cost Rs 628 crore.