Illustrative image – not actual.Odisha Water Supply and Sewerage Board (OWSSB), is likely to complete its sewerage project in the state by February 2015.
The board has already missed its 2011 deadline. Due to slow eviction and tardy land acquisition process, the project has been delayed.
The project requires 214 acre for laying the 412 km sewer line and construction of six sewerage treatment plants. The board has only acquired 110 acre till date. It has so far laid around 150 km pipeline.
The sewerage project, estimated to cost Rs 754 crore, was taken up in 2006. The treatment plants will be set up at Basuaghai (near Tankapani Road), Ebaranga-Kochilaput (near DAV, Pokhariput), Meherpalli, Rokad-Gadakana and Paikarapur.
Odisha Water Supply and Sewerage Board (OWSSB) will soon float tenders for the treatment plants.