Illustrative image – not actual.The High Level Clearance Authority (HLCA) of the Orissa government gave its final clearance to six projects worth Rs.37,989 crore in the power and steel sector. These projects were earlier cleared by the State Level Single Window Clearance Authority (SLSWCA).
Of the total, five projects are from the power sector with a total outlay of Rs.28,704 crore. The power projects have a combined generation capacity of 6,120 MW. Apart from this, one steel project with an investment of Rs.9,285 crore was also cleared.
Details of some of projects are:
-
Ind-Barath Energy Utkal (IBEUL) will be setting up a 700 MW (2x350) thermal power plant at Sahajbahal in Jharsuguda district at an investment of Rs.3,150 crore. IBEUL has acquired 423 acre of the total 550 acre of land required for the project
-
Similarly, Visaka Thermal Power will be setting up a 1,100 MW coal-based power plant at Bhandaripokhari in Bhadrakh district at an investment of Rs.4,800 crore. The project requires 1,200 acre and it will source 36 cusecs of water from Baitarani.
-
L&T's proposal to set up 1,680 MW thermal power project crore near Dhamra in Bhadrakh district at an investment of Rs.10,200 crore was also approved by HLCA. The total land requirement for the project is 1,545 acre. Also, the company will have to settle all the legal issues before signing an MoU.
-
Jindal Steel and Power's (JSPL) proposal to set up a 1,320 MW thermal power plant at Athamallik tehsil in Angul district with an investment of Rs.5,940 crore was also given a green signal by HLCA. It will require 49 cusecs of water and 1,625 acre for the project. Besides, JSPL's proposal to change the configuration of the steel plant in the same location was also approved by HLCA.