Illustrative image – not actual.The Orissa government has accorded its approval to the revised expansion proposal of Orissa Power Generation Corporation (OPGC).
The OPGC - a joint venture company of Orissa government and US power utility, AES Corporation - has a power plant of 2x210 MW power plant at IB Valley near Banaharpal in Angul district.
The expansion will see capacity increase of the OPGC's third and fourth units by 1,320 MW (660x 2). The earlier proposal stipulated two units of 600 MW each.
The Rs 7,000- crore expansion project will be completed by 2013. The financial closure for the project is expected by June.
According to the agreement, the OPGC will offload 50 per cent of power generated from these units to the state grid at the rate fixed by Orissa Electricity Regulatory Commission (OERC).
However, from the third unit of 660 MW, the state will get 264 MW till the fourth unit is commissioned, considering that the plant load factor is expected to be at around 80 per cent. The fourth unit is expected to be commissioned within six months of the commissioning of third unit failing which the OPGC will share 360 MW of power at 80 per cent PLF load with the state grid.