Opa Water Works expansion in Goa awaits certificateIllustrative image – not actual.

The proposed expansion of Opa Water Works in Goa has been delayed as the Water Resources Department (WRD) is yet to issue the mandatory water availability certificate required for project sanction.

The project involves construction of a new 40 million litres per day (MLD) water treatment plant near the existing eight MLD facility, which supplies drinking water to Tiswadi and Ponda talukas. The existing eight MLD plant is also planned to be upgraded to 16 MLD. According to officials, the new treatment plant could take around two to three years to complete, but work cannot proceed until raw water availability is certified by the WRD. The project is primarily aimed at improving water supply to Smart City Panaji and strengthening availability across Tiswadi, Priol and surrounding villages in Ponda taluka.

Opa Water Works currently operates five treatment plants with combined capacity of 152 MLD.