Of the 40 independent power projects (IPPs) expected to come up in the country, the ministry of power has narrowed down its focus to nine projects with a generation capacity of 4,287 MW. These nine projects have a fair chance of achieving financial closure over the next one year.
The power ministry
is actively pursuing with state governments the expeditious implementation of
these projects. It is holding meetings with state government representatives,
institutions and promoters of the projects to expedite the process of financial
closure.
These nine projects
are spread across Madhya Pradesh, Andhra Pradesh, Uttar Pradesh, Gujarat and
West Bengal.
A total of 31 projects, with a cumulative
capacity of 18,715 MW, are unlikely to achieve financial closure in the near
future. The non-availability of escrow cover and inability of the states to
extend guarantees, is the main reason behind this. The capacity of states to purchase
power from new projects is doubtful.
On the other
hand, of the 58 projects cleared by the Central Electricity Authority, 18
projects totalling 6,542 MW, are already on stream or are in the process of
being commissioned. Of these, 10 projects have been commissioned, while eight
are in various stages of construction, according to the power ministry.
Following the
Dabhol imbroglio, the Centre has decided against extending counter-guarantees
to projects coming up in the private sector. Consequently, state governments
have also backtracked on providing guarantees and counter-guarantees, resulting
in projects being stuck. Some projects based on fuels like naphtha, are stuck
on account of the high tariffs in the initial years following commissioning. State
Electricity Boards do not have the funds to purchase expensive power, so the
projects where tariffs may be high, are likely to be stuck. Problems in the
supply of fuel (coal and gas) have also held up some projects.
The government had earlier projected a capacity addition of 26,732 MW and 22,181 MW from private sector projects for the Tenth and Eleventh Plan periods, respectively. However, following the slow progress of the IPPs, the ministry has pruned the capacity addition targets to 7,255- 10,500 MW for the Tenth Plan period. The realisation of capacity addition targets from private sector projects is expected to be 7,035 MW, as against a target of 17,588 MW for the Ninth Plan period (1997-2002).
