Oil and Natural Gas Corporation's (ONGC) field development of western offshore B-193 cluster fields will be completed this year.
This will likely to add 28,000 barrels per day to peak oil production. The B-193 cluster field development includes eight marginal fields -- B-23A, B-28, B-28A, B-172, B-178, B-179, B-180 and B-193 -- off the west coast. The project costing over Rs 8,000 crore will add 44 million barrels of oil production and 6 billion cubic meter of gas over the life of the field.
The project was initially scheduled to be completed by August 2010 but was delayed. While the process platform has been installed, the commissioning will be scheduled in next couple of months. The delay in the project implementation has also resulted in cost overruns by Rs 2,384.66 crore.
Singapore-based Swiber Holdings has installed a 13,000 tonne platform at the B-193 field in the Arabian Sea, off the west coast, using float-over method that will save time and money.