Illustrative image – not actual.ONGC's 726.6 MW (2x363.3) gas based power station in Tripura is unlikely to be completed by 2012.
The Rs 3,500-crore power station being implemented by ONGC Tripura Power Company was slated to be commissioned by March 2012. The 363.3 MW Unit I of the power facility is to be commissioned by December 2011.
However, Phase I of the transmission line - implemented by North-East Power Transmission Company (NEPTC) - is unlikely to be ready before July 2012. The Phase I of the 400-kV double-circuit transmission facility from Palatana in Tripura to Silchar in Assam will be evacuating the entire generation of the first OTPC unit. So far, only 50 per cent work has been completed on the 246-km transmission line. Against a total of 675 towers to be built on the Palatana-Silchar stretch only 261 were ready till March 2011.
And, the 415-km-long Silchar-Bongaigaon transmission project is running behind schedule and is unlikely to be completed before July 2012.
In case of Phase II of the transmission line, NEPTC did not get the requisite forest clearances from the Assam and Meghalaya Governments, which is a prerequisite to get the clearances from the MoEF. Also, the transmission segment was severely delayed due to complications involved in setting up (three) towers over Brahmaputra.