Illustrative image – not actual.Oil & Natural Gas Corporation's coal bed methane project in Jharkhand might be delayed. The first CBM flow that was expected in March 2007 is now expected by August 2007.
The project was delayed first due to delays in awarding the contract, that finally went to a consortium comprising among others, Mineral Exploration Corporation and Shiv Vani Drilling in May 2006. Now the delay is caused due to land acquisition problems. The state administration has been unable to transfer required land in the name of ONGC, it is learnt. Land would be used for creation of physical infrastructure like roads and gas collection centres.
The Jharia block in Jharkhand held by ONGC (74 per cent) and Coal India (26 per cent) is expected to see CBM flows of 3.5 lakh cmd. Apart from this block, ONGC is conducting exploration in the following blocks with partnership of Coal India and Indian Oil Corporation in some.
| Block | State | Equity Stake (%) | ||
| ONGC | Coal India | IndianOil | ||
| Raniganj | WB | 90 | 10 | 0 |
| North Karanpura | Jharkhand | 80 | 0 | 20 |
| South Karanpura | Jharkhand | 100 | 0 | 0 |
| North Karanpura (W) | Jharkhand | 100 | 0 | 0 |
| Bokaro | Jharkhand | 80 | 0 | 20 |
Recursive Links:
ONGC board approves CBM contract (11-May-06)
Related Links:
Project
profile
