Illustrative image – not actual.According to the Union Ministry of Petroleum & Natural
Gas, Oil and Natural Gas Corporation (ONGC) is expected to start commercial production
in the Bassein (Vasai) east offshore, Maharashtra, in the next 3-4 years, i.e.
towards the latter part of the Tenth Five Year Plan period (2002-07).
The Bassein offshore oil
& gas field, which was discovered by ONGC in 2000-01, is said to have oil
reserves of over 65 million tonnes and an equivalent amount of gas reserves.
Following the find, ONGC drilled 3 delineation wells by
June 2002, of which 2 wells were found to have hydrocarbons. One more well is being
drilled. Oil flowed at a rate of 1,500 barrels per day, according to the
ministry.
Presently, ONGC is evaluating the extent of
recoverable reserves and is charting out a development programme for the
region.
To further enhance oil and gas recovery, ONGC proposes
to further delineate the structure and 3D seismic survey are planned to be
carried out during 2002-03.