Illustrative image – not actual.ONGC plans to invest Rs.5,700 crore to increase the production of Neelam Heera offshore oilfields near Bombay High.
The company is planning to upgrade the compression facility, re-develop Neelam Heera, optimize the gas-lift system, integrate and optimize surface facility between Neelam and Heera fields, install new platform and drill 45 new wells. The current fuel recovery from the oil field will be raised from 28 per cent to 35 per cent after expansion.
The redevelopment project will give ONGC an additional annual revenue of Rs.260 crore through the production of 9,12,500 barrels oil. The current capacity of Neelam Heera stands at 1,500 barrels per day (bpd) and will be raised to 4,000 bpd after redevelopment.
The development plan is being submitted to the management by end-December 2003 and is awaiting financial clearance. The project is scheduled for completion by 2009.