Illustrative image – not actual.Oil & Natural Gas Corporation is planning to develop its three B-series offshore marginal gas fields located closer to Mumbai High North oil field with an an estimated cost of Rs.2,000 crore.
The company is likely to seek board approval in this regard by April 2007.
The fields to be developed are B-48, 105 and 46 and these three reserves are expected to produce roughly 1.75 mmscmd of natural gas a day. The gas produced from the fields will be taken to the MHN platform for processing.
The project is a part of the company's plan to finalise development of 29 offshore marginal fields around Mumbai High with an estimated production capacity of 12-15 mmscmd and six million tonne of oil by March 2008. The estimated total investment is estimated between Rs.8,000 crore and Rs.10,000 crore. The projects are expected to be commissioned during the next three years.
Also See:
ONGC completes one year of production in its marginal field (27-Feb-07)