ONGC has planned to invest Rs.700 crore in stepping up gas production from Tripura from 1.7 mmscmd to 4.5 mmscmd by 2007. 

Apart from drilling four new wells, the plan also includes setting up of three new gas stations and laying a pipeline connecting the production wells to the power plant. 

The gas infrastructure revamp is being done to meet the fuel requirements of the proposed 750 MW power plant in the state. The plant would require 3.75 mmscmd of gas to run on full capacity.

ONGC has decided to set up the plant at Palatana in South Tripura district, 50 km away from Agartala. The previous location, Sonamura, was changed due to its proximity with the Bangladesh border. The Tripura state government has allotted 175 ha of land and an additional 50 ha would soon be made available to ONGC.