Illustrative image – not actual.ONGC has tied-up Rs 2,224 crore debt from PFC for its proposed 700 MW power plant at Tripura.
ONGC Tripura Power Company (OTPC), a JV of ONGC, IL&FS and the Tripura Government is setting up the 2x363.3 MW gas based power plant at Pallatana in Tripura. The Rs 3,400 crore project is to be commissioned in March 2012.
The project will use natural gas from ONGC's fields in Tripura for generating electricity. About 87 per cent of the power generated is to be sold to all the North East states.
The electricity generated at the power plant is expected to be evacuated through a 656 km long line from Pallatana to Bongaigaon in Assam to be constructed at an estimated cost of Rs 1,770 crore. This line will be implemented by North East Transmission Company, an SPV jointly promoted by OTPC, PGCIL and all the North Eastern states.
Also See:
OTPC invites bids for Palatana power project (07-Dec-09)
Related Links:
Project profile