ONGC projects face delay Illustrative image – not actual.

A number of ONGC’s major ongoing projects are facing delay due to various hurdles.


The Petroleum Ministry’s monitoring cell has found that nearly half of the ongoing projects, worth Rs 41,259 crore, are running behind schedule by about nine-ten years.


It has been learned that development of many of ONGC’s small and cluster fields have been delayed.


Several issues are affecting the pace of the projects. Some of these include slow progress in the engineering and installation process, technological hiccups, claims and counter claims by contractors, delay in material supply and additional cost claims by contractors. In many cases, ONGC had to terminate the contract after contractors failed to submit performance bank guarantees.

 

Below is a list of the projects facing delay:

 

  • Integrated development of the G-1 and GS-15 fields which were approved at a cost of Rs 1,263 crore and were slated for completion by April 2006. Due to delay, the estimated cost of the project is now Rs 3,437 crore and is expected to be completed by June 2015
  • C-series field which was approved at a cost of Rs 3,195.16 crore and was expected to be completed by December 2008. As per the revised plan, the estimated cost of the project is now Rs 3,690.37 crore, to be completed by May 2015
  • B-22 cluster fields worth Rs 2,323.4 crore, which was due to be completed by September 2010 will now cost Rs 2,920.82 crore. The new deadline for the project is December 2015
  • B-193 cluster fields worth Rs 3,248.78 crore, which was slated for completion by August 2010. The new deadline for the project is May 2015
  • Construction of 12 offshore vessels worth Rs 736.65 crore which was due for completion by September 2011. As per the revised deadline, the project is now scheduled for completion by December 2015

 