Having failed to acquire the minimum land to start commissioning the CBM development and exploration programme in Jharkhand, ONGC may re-negotiate the terms and contracts with the project contractor.

The company had awarded a turnkey contract to Mineral Exploration Corporation Ltd (MECL) led consortium in May 2006 to drill 14 development wells and 22 pilot wells in the discovered fields of Jharia and Bokaro. As per the contract specification, ONGC was scheduled to offer a minimum work of four wells and one gas collection station to MECL for commissioning of the project.

However, almost a year since the contract was awarded, ONGC could acquire land for merely four wells. Even the requisite land for creating the necessary road infrastructure could not be acquired in full.

The Directorate General of Hydrocarbons has already granted six months extension ending on August 2007 to ONGC to complete the Phase I work programme in Jharia block held jointly with CIL (10 per cent). ONGC had already established reasonably high rate of CBM flow from one pilot well in the block, secured on nomination basis. The company, however, is relatively safely positioned in the case of CBM Policy I (2001) Bokaro block where Phase I programes were cleared in 2006 and pilot wells are scheduled to be drilled followed by development drilling by 2009. The block is held with Indian Oil (20 per cent).

Also See:

ONGC to commission coal bed methane project by April (07-Mar-07)

← All latest storiesBack to top →