Illustrative image – not actual.ONGC is likely to get an extension to complete the minimum work programme in Bengal offshore block. The company has sought extension on grounds that formal communication for the last extension in 2006 was received late. A final decision in this regard is expected to be taken at the ministerial level.
However, the Directorate General of Hydrocarbons is of the opinion that as per the provisions of the production-sharing contract, an extension of only six months can be granted to the operator for completing the committed work programme.
On the other hand, an additional 12 months was granted under the new extension policy. ONGC, the operator for the block, has therefore would be granted extension of 18 months in respect of WB-OSN-2000/1.