ONGC faces hurdles for Unit-II of Palatana project Illustrative image – not actual.

ONGC is facing problems in commissioning Unit-II of its Palatana gas-based power project at Palatana in South Tripura.


As a result, the transmission line associated with Unit-II of the gas power plant is also facing commissioning delays.


The 726.6 MW power project, being developed by ONGC Tripura Power in two units, each with 363.3 MW capacity, is estimated to cost Rs 4,000 crore. The company has already commissioned Unit-I of the project in October 2012. 


ONGC is likely to commission the Unit-II by December 2013, while the transmission system required for evacuation of power from the Unit-I has already been commissioned.


The transmission line from Byrnihat (Meghalaya) to Bongaigaon (Assam), is facing key challenges like stoppage of work at various locations due to stay orders from courts for severe right of way (ROW). Delay in getting permission from the state government to cut 118 trees for the unit is also another problem faced by the developer.