ONGC's D-1 field located in the deep continental area of Mumbai offshore has started production with the first development well flowing. On completion of other wells, it is expected to produce 9,000 bpd.
The development of the D-1 field will be implemented in two phases. Currently Phase I of development is under implementation, wherein three producers and three injectors is planned for drilling and completion. The Phase II of the project also envisages three producers and three injectors after evaluating the production performance of the first phase.
To exploit oil and gas from 255 sq km D-1 structure, a 12-slot well-cum-water injection platform and control system for electrical submersible pumps and chemical injection system has been installed.
The produced well fluid is to be processed at early production system (EPS). The bridge 'Sagar Laxmi' connected to the D-1 platform is been modified and upgraded by installation of DCS (digital control system) for process control and other infrastructural facilities required for exploiting hydrocarbons.
This being an isolated and marginal field, the oil produced after processing will be transported from EPS through SBM (single-buoy mooring) for offloading into an oil tanker for onward transportation to refinery.