ONGC has terminated USD 152 million contract awarded to Mercator Oil & Gas in 2011 for converting its offshore drilling rig, Sagar Samrat, into a mobile offshore production unit.

Sagar Samrat is India’s and ONGC’s first drilling rig, built in 1973 by Japanese firm Mitsubishi. The rig-conversion contract was to be completed by May 2013 as per the original timeline stipulated in the November 2011 deal.

The 69-month delay has raised the project cost by 46 percent to Rs 1,256.72 crore. ONGC has so far spent Rs 1,195.34 crore on the contract which is expected to be completed by December 2018.

It had taken delivery of the jack-up rig in 1974 and after drilling 131 wells, the rig was decommissioned in 2005. In September 2018, ONGC notified Mercator Oil & Gas of its intention to terminate the contract after issuing 14 days’ notice and also moved to encash the bank guarantee of USD 15 million submitted by the contractor through Axis Bank.

The parent company Mercator has given corporate guarantee for the conversion contract and ONGC has indicated that it will recover liquidated damages from the contractor.

The delay has been cited to the increase in scope of work post-award of contract due to legs of Sagar Samrat failing in in-place analysis as per ABS guidelines necessitating replacement of all its four legs, delay in procurement of steel and slow progress of fabrication of legs by the contractor.