Illustrative image – not actual.On 18 November 2013, one arm of the Kapurbawdi flyover was inaugurated.
The project was inaugurated by Prithviraj Chavan, Chief Minister of Maharashtra, and Deputy Chief minister, Ajit Pawar. This part of the bridge was slated for inauguration on November 15, but was postponed due to some issues.
This part of the flyover, which goes from Mumbai to Ghodbunder, will ease traffic congestion from Majiwada to Kapurbawdi junction.
Work on the flyover had begun in February 2010, but its completion has been delayed for more than three years. Maharashtra State Road Development Corporation (MSRDC) has undertaken the project for the 767 mtr long flyover which will be opened in three phases.
The estimated cost of the project was Rs 166 crore. Due to delays, the construction cost of the project has now shot up to Rs 197 crore.
Work on the other arms of the flyover will be completed by 2014.