Illustrative image – not actual.After dragging its feet over the Rs.7,500
crore Bina refinery project in Madhya Pradesh, Oman Oil Company (OOC) has finally
walked out of it. OOC was to implement the project in joint venture with Bharat
Petroleum Corporation Ltd (BPCL).
OOC’s decision is based on its internal
study as well as on a report prepared by a consultant. The reports had revealed
that the project is unlikely to yield an acceptable rate of return.
BPCL, on the other hand, still has faith in the viability of the project. It has communicated to the Union Ministry of Petroleum and Natural Gas that it will go ahead with the project on its own.
The project envisages a 6 million
tonne refinery and a 943 km long crude oil pipeline. The project, when conceived
in 1995, was estimated to cost Rs.5,172 crore. However, it suffered time
overruns for want of environmental and forest clearances. The project cost consequently
rose to a steep Rs.7,500 crore.
OOC which has invested $30 million
in the project, will retain an equity interest equal to the ratio of this
investment in the project.