Olkaria-Narok transmission line project in Kenya nears completionIllustrative image – not actual.
The construction work is nearing completion for the Olkaria-Narok transmission line project in Kenya nears completion. The 63 km line is expected to be completed by November 2021.

The project is 80 percent complete, and all the foundation works were already done with only the erection of 20 towers remaining before the project is commissioned. Once this project is completed, power outages in Narok and its surrounding areas will be a thing of the past.

The system improvement project commenced on 15 July 2019 and involves the construction of the 68 km 132 kV double circuit transmission line from Olkaria to Narok, a new 132/33 kV substation at Narok, and an extension of the existing Olkaria substation.

China CAMC Engineering Company was awarded the contract to develop the project. Upon completion, the line will increase electricity access within Narok County and its surrounding areas.