Energy Infrastructure India Ltd (EIIL), the wholly-owned subsidiary of Energy Infrastructure Group, Sweden has pushed its Rs 500 crore petroleum jetty project at Okha, near Jamnagar on the back burner owing to slowdown and extension of subsidy on LPG till 2010.

Apart from recession, several reasons have been cited for the delay in project, the main being land acquisition problems. EIIL could take possession of only 42 acre of government wasteland of the allotted 98 acre.

So far, EIIL has invested Rs 150 crore in the Okha project. Besides, it has hired London based Tsakos Shipping to import LPG and drawn up plans to sell it under the brand "Max Gas".

The gas will be transported to Jamnagar through a 140 km pipeline and this will connect to the existing Jamnagar-Loni pipeline to distribute the gas in north India. For this, EIIL has tied up with GAIL for constructing the Okha-Jamnagar pipeline. However, GAIL is yet to be allocated land for putting up their receiving/pumping station for EIIL.

The company has also tied up with Infrastructure Lease & Financial Services for partially financing the project.