Illustrative image – not actual.Ministry of Petroleum and Natural Gas has decided to cancel permits issued to Reliance Gas Transportation Infrastructure (RGTIL) to lay four natural gas pipelines citing inordinate delays in construction of the 2,175-km lines.
However, a formal letter cancelling the authorisation is yet to be issued as the file is pending approval of S Jaipal Reddy, Minister of Petroleum and Natural Gas. The ministry was not ready to accept RGTIL's argument that the government has already allocated all of the projected 91 mmscmd gas output from the KG-D6 fields to customers in Andhra Pradesh, Maharasthra and other northern states, leaving no gas for transportation through its proposed pipelines from Kakinada to Howrah, Chennai, Tuticorin and Mangalore. Also, the ministry rejected the company’s assertion that it has done all ground work including route survey, pre- engineering and acquisition of right of use (ROU) and it would start work the moment government identifies a source of gas that would feed the pipelines.