Odisha to renovate 3 hydel projectsIllustrative image – not actual.
Government of Odisha has decided to renovate three major hydro-power stations.

The hydel-power stations at Hirakud, Chipilima and Balimela will be renovated in phases with an investment of about Rs 887 crore.

The government will renovate two units of Hirakud power station (37.5 X 2) by investing Rs 158 crore. While the 34 MW power station at Chipilima will be renovated at an estimated amount of Rs 65.67 crore and the work will completed in 20 months.

The 510 MW Balimela Hydel Project will be renovated at an investment of Rs 664 crore.

More Project Info: Hirakud Hydel Power Project - Renovation