Illustrative image – not actual.While Rs 10 crore will be spent on construction work, Rs 70 crore will be spent to acquire private land required for the project in this fiscal. Private land of 700 acre is to be acquired by 2015-16 end.
The Railways will also spend Rs 10 crore towards construction work under the project this fiscal. The total expenditure under the project in 2015-16 will thus be Rs 90 crore.
The state government has identified land for project work up to 19 km and has paid Rs 8 crore to ECoR in this regard. The 19 km railway work from Bolangir will begin in December 2015.
Out of a total of 289 km under the project, work has been completed on a stretch of 41.5 km up to Rajsunakhala from Khurda. At present two up and down passenger trains are plying from Khurda to Rajsunakhala. Work on the stretch up to Bolagarh will be completed by June 2016, while the work on the stretch up to Nayagarh will end by March 2017. Work is also underway on the Daspalla-Bolangir track under the project.
Related Project Info: Khurda Road-Bolangir SL Railway Line
