Illustrative image – not actual.The scope of work will include milk reception, processing, packing, 60 klpd UHT plant, 10 klpd ice cream plant, product manufacturing, 20 tpd powder plant, services and utilities, along with structural and civil construction work. The contractor for the project is the National Dairy Development Board.
As per the latest development available with Projects Today, work awarded to Goel Construction for civil, structural, water supply, sanitary and other miscellaneous works such as internal electrification works for milk powder plant, UHT, administration and workers amenities including roads and hard park was underway. The project will be executed by October 2020.