Illustrative image – not actual.NTPC Vidyut Vyapar Nigam (NVVN), is planning to generate a total of 990.5 MW through Grid Connected Solar Power Projects under Jawaharlal Nehru National Solar Mission (JNNSM) till 2014-15.
As per the quarterly performance review for the 4th quarter of last fiscal (January-March 2013), 242.5 MW capacity projects are likely to be completed by December 2013, which will result in the total capacity shooting up to 720.5 MW. Additionally, an increase of 270 MW capacity from Batch-I is likely to be generated during 2014-15.
Of the total capacity addition till the year end, 80 MW is likely to be generated by June-July 2013, which comprises 50 MW from Batch-I and 30 MW from Batch-II. And projects with a total capacity of 162.5 MW are expected to be completed between July and December 2013.
The company has already commissioned 478 MW capacity projects so far, which comprise 130 MW from Batch-I, 300 MW Batch-II and 48 MW of Migration projects.