NVVN selects seven bidders for solar projectsIllustrative image – not actual.

The NTPC Vidyut Vyapar Nigam (NVVN) has selected seven bidders to build 479 MW solar power projects in the first phase of the Jawaharlal Nehru National Solar Mission (JNNSM).

Reliance Power, Lanco and KVK Energy are to develop 100 MW capacity each. Megha Engineering, Godavari Power and Corporate Ispat will build solar plants of 50 MW each while the balance capacity will be developed by Arum Renewables.

NVVN is expected to issue LoI to selected bidders by end-2010 and PPAs will be signed by February 2011. Developers are required to achieve financial closure for allocated projects within six months and commission them within two years from the date of financial closure.

Also See:

Companies vie for projects under solar mission (19-Nov-10)

← All latest storiesBack to top →