NTPC's Rihand power plant fully commissionedIllustrative image – not actual.

National Thermal Power Corporation has sychronized the fourth unit of the Rihand power project to the northern grid. With this, the coal-based power plant's total capacity stands at 2,000 MW.

The Rihand power project in Sonbhadra district of Uttar Pradesh has four units of 500 MW each. The plant began operations in March 1988 when the first unit of 500 MW was commissioned. The second unit was commissioned in July 1989.

The expansion project of adding two more units of 500 MW was initiated in early 2000. The third unit of 500 MW was made operational in February 2005, eight months ahead of schedule.

Bharat Heavy Electricals was the EPC contractor for the expansion project with a contract value of Rs.2,079 crore.

With the commissioning of the fourth unit, NTPC's total installed capacity stands increased to 24,249 MW through its 13 coal-based power plants and seven gas-fired plants.

Also See:

NTPC scales up capacity addition targets (24-Sep-05)