Illustrative image – not actual.NTPC’s 4,000 MW ultra mega power project at Kudigi in Bijapur district of Karnataka is yet to receive approval from the MoEF.
The NTPC board has approved a proposal to take up the work for the Stage I of 3x800 MW project. Once the MoEF nod comes, the company is expected to begin civil work on the Stage I. The Karnataka Industrial Area Development Board (KIADB) has handed over 1,923 acre for the project. The Stage II of 2x800 MW will be taken up after the KIADB transfers the remaining 1,600 acre for the project.
Meanwhile, about 1,100 acre for construction of Ash Dyke is under notification for acquisition. The company has included the Kudigi plant equipment in the bulk tendering issued for many other projects. The first unit will be operational in 58 months from the date of award of contract for the main plant equipment.