Reliance Industries has stated that it was committed to supplying gas to NTPC's upcoming Kawas and Gandhar power projects in Gujarat. Reliance, however, is unwilling to accept the "unlimited liability" clause mentioned in the Gas Sale & Purchase Agreement.

Reliance is willing to supply gas at $2.86 per mmbtu. In case of disruptions, Reliance would arrange for alternate supplies but would not bear the price difference, if any. In other words, if the cost of the alternate gas exceeds $2.86 per mmbtu, NTPC would have to pay for the difference.

Meanwhile, NTPC has demanded that Reliance should not enter into any other gas supply contracts. On its part, Reliance has assured NTPC that even if Reliance were to enter into other contracts, it would not hurt the prospects of NTPC's projects.

NTPC had moved the Mumbai High Court on 20 December 2005 after Reliance Industries refused to sign the Gas Supply & Purchase Agreement.

Also See:

Gas supply agreement: NTPC mulls legal action against Reliance (09-Dec-05)

← All latest storiesBack to top →