NTPC to synchronize Unit-I Barh plant by July 2013Illustrative image – not actual.

NTPC is likely to synchronize Unit-I of the 660 MW super thermal power plant, stage-II, at Barh in Patna district of Bihar by July 2013.

 

Bihar state will get 50 per cent of the 660 MW unit as per the agreement with the Union Ministry of Power. The remaining 330 MW will be given to Jharkhand (6.06 per cent), Orissa (12.57 per cent), West Bengal (15.8 per cent) and Sikkim (1.29 per cent), among others.

 

The total approved cost of stage-II is Rs 7,688.12 crore, out of which Rs 7,674.77 crore has already been invested by the company.

 

Similarly, the total approved cost of stage-I (3x660 MW) is Rs 8,692.97 crore of which Rs 7,674.77 crore has already been spent on the construction and execution works.
 