Illustrative image – not actual.NTPC may start production from its three captive coal mines -- Chatti Bariatu, Chatti Bariatu (south) and Kerandari, in Jharkand, by June 2016.
Chatti Bariatu (south) coal block, which is located in the dip-side of Chatti Bariatu block in North Karanpura coalfields, is expected to be developed by 23 January 2038, i.e. 25 years after completion of Chatti Bariatu coal block.
Earlier, the three coal blocks were taken away from NTPC by the coal ministry, as NTPC had failed to develop them within the stipulated time frame. However, later, the blocks were returned to NTPC after it received approval from the law ministry.
Apart from this, all requisite clearances such as mining plan, mine closure plan and environment and forest clearance have been received for the Chatti Bariatu coal block.
Taking into consideration the Kerandari mine, all requisite clearances like mining plan and environment clearance have been completed; but forest clearance (Stage-II) and land acquisition are still under process.
As far as the Chatti Bariatu (south) mine is concerned, geological reserves have been procured and a mining plan is under examination by the ministry of coal.