| NTPC: At a Glance* | ||
| Fuel | Nos. | MW |
| Fully owned | ||
| Coal | 13 | 19,980 |
| Gas | 7 | 3,955 |
| Joint Ventures | ||
| Thermal | 3 | 314 |
| Total | 23 | 24,249 |
| Under Construction | ||
| Coal | 7 | 8,170 |
| Hydro | 1 | 800 |
| Total | 8 | 8,970 |
| *As of December 2005 | ||
NTPC, on 14 February 2006, signed a Medium Term Note agreement to raise up to $1 billion in international debt. The agreement will facilitate the raising of medium term funds on regular basis from the international debt market.
NTPC has mandated Barclay's Capital (a division of Barclays Bank, Plc) and Deutsche Bank AG as lead arrangers of the programme that has obtained BB+ rating from both Fitch and S&P.
Funds mobilised will finance NTPC's endeavour of becoming a 40,000 MW power generating company by 2012. NTPC is in the midst of implementing projects with nearly 9,000 MW of capacity (including 800 MW of hydropower; see table), which would be commissioned over the next 2-3 years. The international debt would mainly finance these projects.