NTPC to negotiate prices with BHEL for Rihand and Ramagundam projectsIllustrative image – not actual.

National Thermal Power Corporation (NTPC) has decided to negotiate prices with Bharat Heavy Electricals (BHEL) for the equipment supply contracts for the Rihand and Ramagundam thermal power projects. BHEL was the sole bidder for the projects.

 

The total cost of the two projects is Rs.6,000 crore and the combined capacity is 1,500 MW.

 

For the two units of 500 MW each of the Rihand project in Sonbhadra district of Uttar Pradesh, BHEL had quoted Rs.2,375 crore. For the 500 MW Ramagundam project in Karimnagar district of Andhra Pradesh, BHEL had quoted Rs.1,315 crore. The NTPC board will take a decision on the award of contract by February 2001.