Illustrative image – not actual.National Thermal Power Corporation (NTPC) plans to invite global bids, by the end of May 2001, for the supply of equipment and erection of Stage I of the Sipat power project in Chhattisgarh.
The 1,980 MW project consists of three units of 660 MW each. NTPC plans to use super critical technology boilers for the project. Construction work is likely to commence by mid-2003 and all three units are expected to be completed by 2006-07.
The project has been cleared by the Central Electricity Authority.
The project, estimated to cost around Rs.7,600 crore, would be financed through internal resources to the extent of 30 per cent. The remaining funds would be raised from financial institutions, bonds and foreign syndicated loans.