NTPC will invest about Rs 1,000 crore in setting up railway infrastructure in Karnataka.
On 8 June, 2016, NTPC and South Western Railways signed an agreement for doubling of Hotgi-Kudgi section of South Western Railway, under Customer Funding Concession.
NTPC has already deposited Rs 946 crore with South Western Railway towards the cost of doubling of railway section between Hotgi - Kudgi (134 km). The section between Hotgi - Kudgi consists of 10 block stations, eight major bridges and two important bridges on river Don and River Bheema.
Work for doubling has already been started by South Western Railway and the project is targeted for completion by March 2020. The augmented rail infrastructure will cater to the coal transportation requirements of the 4,000 MW power project of NTPC.