NTPC to infuse additional equity in RGPPL's Dabhol projectIllustrative image – not actual.

NTPC, which currently holds 28.3 per cent equity in Ratnagiri Gas & Power's 2,150 MW Dabhol plant, is considering an infusion of Rs.500 crore as an additional equity into the project to part-finance the completion of the liquiefied natural gas (LNG) terminal.

NTPC, along with other stakeholders of RGPPL - Gail India and Maharashtra State Electricity Board (MSEB) - was asked by the Empowered Group of Ministers (EGoM), headed by external affairs minister, Mr.Pranab Mukherjee, to work out the options for completing the LNG terminal.

The MSEB, which holds 15 per cent equity in RGPPL, has also offered around Rs.250 crore as additional equity, or the funds required as per the proportion of its stake in RGPPL.

The LNG terminal requires Rs.1,200 crore for its completion and the total funding required for completing the three power blocks along with the LNG terminal is estimated around Rs.2,200 crore.

Also See:

Maharashtra to invest in LNG terminal at Dabhol (06-Aug-07)

← All latest storiesBack to top →