NTPC to commission Lata Tapovan project by 2017Illustrative image – not actual.

NTPC is likely to commission its Lata Tapovan hydroelectric power project in Uttarakhand by August 2017.

 

The construction of 171 MW project is expected to be completed by December 2016, which will result in commissioning of the project in August 2017.

 

In 2012, NTPC awarded the contract for the project to L&T Construction. However construction was stalled due to opposition by local villagers at the barrage area of the project.

 

Work on the approach road to power house commenced in January 2013, and road formation cutting is in progress. Construction of power house and head race tunnel is likely to be completed by October 2016.

 

In addition to this, the NTPC also expects to complete switchyard works by September 2016 and all hydro mechanical works including spillway gate, HRT intake gate, surge shaft gate, draft tube gate, etc by December 2016.

 

Related Link:
Project profile

 

← All latest storiesBack to top →