NTPC and Tamil Nadu Energy Company Ltd, a 50:50 JV between NTPC and the Tamil Nadu Electricity Board (TNEB) will go on stream by 2011-12. NTPC is planning to add an additional 2,950 MW to the southern grid by the year of 2011-12 and the new capacity will be created in Tamil Nadu and Kerala.

The coal-fired power station will have an installed capacity of 1,000 MW and the entire installed capacity will be synchronised by 2011-12.

NTPC has floated the Tamil Nadu venture following the shelving of a number of IPPs approved by the Central Electricity Authority (CEA) raising the fear that the State may miss the planned addition of generating capacity. The project has got coal linkage from ministry of coal following the request by the Union power ministry.

According to the in-principle agreement, the power station will get five million tpa of coal from Mahanadi Coal Fileds Ltd (MCL), a subsidiary of Coal India Ltd.

The NTPC-TNEB combine has approached the Centre for getting the mega power project status for the project. The project is slated to come up at Ennore in the outskirts of Chennai.

NTPC is expected to complete the second phase of its Kayamkulam expansion plan by 2011-12. The Kayamkulam second phase will have an installed capacity of 1,950 MW and the entire new capacity will be commissioned in the same period.

The Kayamkulam expansion programme has been cleared by all the authorities concerned including the NTPC board. NTPC will be executing the project entirely by its own without any equity participation from other parties.

With the completion of both the projects, NTPC's capacity in the region will go up by a significant 1,950 MW and the additional power will be shared among the four southern states of Kerala, Tamil Nadu, Andhra Pradesh and Karnataka besides the Union Territory of Pondicherry.